Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Current Status | ||
---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | |||
Project Milestone-I | 150 | 20% | 08.08.2022 | 20% | 06.10.2022 | |
Project Milestone-II | 330 | 35% | 03.02.2023 | 35% | 31.03.2023 | |
Project Milestone-III | 510 | 75% | 67.97% | |||
Schedule Completion | 730 | 100% |