Project Milestones

Project Milestones

Project Milestone Description (Days from Appointed Date) Planned Actual Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 150 20% 08.08.2022 20% 06.10.2022  
Project Milestone-II 330 35% 03.02.2023 35% 31.03.2023
Project Milestone-III 510 75%       67.97%
Schedule Completion 730 100%